Manhattan IL Route 52 Projects and Where Each One Stands

The Piercy Property Pulse  |  Local News  | 

By REALTOR®Real People Realty in Mokena, Illinois. Last updated October 21, 2026.

The short answer

Manhattan, Illinois has five projects on or near U.S. Route 52, by village reports read October 19, 2026. Ivanhoe's turn lanes started by September 1, and Front Street parking work is set to start the week of October 26. A water main is set for spring 2027. Crosswalks at Wabash and Whitson wait on an IDOT permit; a path to Round Barn Farm waits on an IDOT grant.

You want to know what is changing on U.S. Route 52 in Manhattan before the cones go up. The village does publish it, but its October 20, 2026 board packet runs 187 scanned pages, and the engineer's project table sits on page 186. [1]

Below is each project on or near Route 52, what the village's own papers say about it as of October 19, 2026, and the page that says it.

Key facts

Ivanhoe turn lanes on U.S. 52

Started by September 1, 2026; the village hopes to finish them this winter [6]

Front Street parking lot and resurfacing

Low bid $314,945.70 from Austin Tyler, on the October 20, 2026 board agenda [2]

Front Street construction start

The week of October 26, 2026, per the engineer's October report [1]

U.S. 52 water main, Gougar Road to Foxford Drive

Design and bid documents in progress; construction set for spring 2027 [1]

Crosswalks at Wabash and Whitson

Resubmitted to IDOT for a permit on August 20; waiting for IDOT to respond [1]

Multi-use path, Foxford Drive to Round Barn Farm

Grant application sent to IDOT on October 5, 2026; schedule depends on funding [1]

What the ITEP grant would pay

80% of eligible design and construction costs, with a 20% local match; $5 million at most [3]

Have a question about your own home? Call or text Chris at (815) 205-0395.

Ivanhoe turn lanes: started by September 1

Work on the U.S. Route 52 turn lanes into the Ivanhoe subdivision in Manhattan had started by September 1, 2026. At the Village Board meeting that day, village staff said that "Route 52 has started with the turn lanes going into the subdivision." Staff said the village is working with the developer to finish the turn lanes, landscaping and punch list items. The goal, in staff's words: "We are hoping to have that completed by this winter." [6]

The village's September 2026 building report shows 15 occupancies issued in Ivanhoe from May 1 to September 30, 2026. An occupancy is the village's sign-off that a finished home can be moved into. The same report shows no new Ivanhoe building permits in those five months. A year earlier, from May 1 to September 30, 2025, there were 14. [8]

Front Street parking: work set to start the week of October 26

The Village of Manhattan plans new parking along Front Street, which runs to U.S. 52. The same project resurfaces Front Street, according to a memo from the Superintendent of Public Works dated October 12, 2026. The memo says the street needs it because of the watermain replacement project and damage from its heavy equipment. Sidewalk repairs and improvements are part of the work. [2]

  • Where: the engineer's October 2026 report describes on-street parking along the east side of Front Street from Sweedler to U.S. 52. [1] The plan set covers Front Street from Elwood Road to U.S. 52, 966.87 feet, or 0.18 miles. [2]
  • Bids: four. Austin Tyler bid $314,945.70, D Construction $338,392.10, P.T. Ferro $369,388.20 and Gallagher Asphalt $402,362.80. [2]
  • Board action: the memo puts a resolution to hire Austin Tyler for $314,945.70 on the Village Board's October 20, 2026 agenda. Staff recommends approving it. [2]
  • When: the engineer's October 2026 report says construction is to start the week of October 26. [1] The memo says Austin Tyler indicated it can finish before the end of 2026. [2]

Wabash and Whitson crosswalks: waiting on an IDOT permit

Manhattan plans crosswalks with signage at Wabash and Whitson along U.S. 52. The village engineer's September 2026 report says the design for the crosswalks, signage and flashing beacons is complete. [7]

The crosswalks need a permit from IDOT, the Illinois Department of Transportation. The engineer's October 2026 report says the village resubmitted for that permit on August 20 and is waiting for IDOT to respond. The schedule is to be determined pending IDOT coordination. [1]

Neither report gives a cost for the crosswalks.

Water main extension: construction set for spring 2027

The U.S. 52 water main extension runs from Gougar Road to Foxford Drive in Manhattan. The village engineer's October 2026 report says design and bid documents are in progress and lists spring 2027 for construction. [1] The September 2026 report gave the same schedule. [7]

Route 52 path to Round Barn Farm: waiting on a grant

Manhattan wants to extend the existing multi-use path along U.S. 52 from Foxford Drive to Round Barn Farm. A September 9, 2026 memo from Village Engineer Carrie A. Pintar says the project "will increase safety by providing a dedicated path for bicyclists/pedestrians" between the two. The board's resolution calls it bicycle and pedestrian facilities with crosswalk improvements along U.S. 52. [3]

Most of the money would come from IDOT's Illinois Transportation Enhancement Program, or ITEP. The memo calls ITEP a $157 million federally funded program run through the state. [3]

  • The ITEP grant pays 80% of eligible design engineering, construction and construction engineering costs. The village pays a 20% local match. [3]
  • The ITEP grant pays 50% of right-of-way and street lighting costs, per the resolution. Right-of-way is the land a road or path sits on. [3]
  • The largest award for one project is $5 million. [3]
  • The memo lists the cost to the village as to be determined if the grant is awarded.

The Village Board approved a resolution supporting the application on September 15, 2026, with 6 ayes and 0 nays. A trustee asked that night whether the post office, across the street from the planned path, could be part of the application. The village engineer said it can be included. [4]

On October 6, 2026, the village engineer told the board the application went to IDOT the day before. The village will follow up once it learns whether it gets the grant. [5] The engineer's October 2026 report gives October 5 as the submission date. It says the right-of-way and easement research is complete, and that the schedule depends on available funding. [1]

What this means if you live near Route 52

If you own or are looking at a home near U.S. 52 in Manhattan, the village's papers set two dates. Front Street work is set to start the week of October 26, 2026, and water main construction is set for spring 2027. [1] The path to Round Barn Farm and the Wabash and Whitson crosswalks have no date yet. One waits on a grant decision and the other on an IDOT permit. [1]

Sources

  1. Village of Manhattan, Village Engineer Monthly Report, October 2026. Read October 19, 2026. Village Board packet for October 20, 2026, page 186.
  2. Village of Manhattan, Board of Trustee memo and resolution, Front Street Parking Lot and Front Street Resurfacing Project, October 12, 2026. Read October 19, 2026. Village Board packet for October 20, 2026: memo page 105, resolution page 107, plan cover sheet page 111.
  3. Village of Manhattan, Village Engineer memo and resolution on the IDOT ITEP grant application, September 9, 2026. Read October 19, 2026. Village Board packet for September 15, 2026: memo page 59, resolution page 61.
  4. Village of Manhattan, Regular Minutes of the Board of Trustees, September 15, 2026. Read October 19, 2026. In the Village Board packet for October 6, 2026, pages 5 and 6.
  5. Village of Manhattan, Regular Minutes of the Board of Trustees, October 6, 2026. Read October 19, 2026. In the Village Board packet for October 20, 2026, page 8.
  6. Village of Manhattan, Regular Minutes of the Board of Trustees, September 1, 2026. Read October 19, 2026. In the Village Board packet for September 15, 2026, page 12.
  7. Village of Manhattan, Village Engineer Monthly Report, September 2026. Read October 19, 2026. Village Board packet for September 15, 2026, page 81.
  8. Village of Manhattan, Building Report, September 2026. Read October 19, 2026. Village Board packet for October 20, 2026, page 187.

Related reading

About the author

Chris Piercy is a REALTORĀ® with Real People Realty and leads the Piercy Sells Group, based in Will & Grundy County, Illinois. He helps people buy and sell homes in Wilmington, Braidwood, Coal City, Diamond, Morris, Manhattan, New Lenox, Mokena, Channahon and Shorewood, and across Will and Grundy counties. Chris is a Top 1% Realtor in Illinois with 70+ five-star reviews.

Office: 9981 W 190th St, Unit H, Mokena, IL 60448. Call or text (815) 205-0395. Website: .

Reviews and profiles: Zillow, Realtor.com, Facebook, Instagram, LinkedIn, YouTube, TikTok, X.

Talk to Chris

Have a question about buying, selling or your own home in Will or Grundy County? Call or text Chris. Who YOU use Matters!

Call or text (815) 205-0395

Real People Realty, Illinois  |  Equal Housing Opportunity

Work With Chris

Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact me today.